Tarbert Harbour Slipway Project: Construction Progress Update

Work continues on Tarbert Harbour’s new access slipway and car park development.

With significant progress being made on the foundations and protective structures needed for the new facility.

Drone shot: aerial view showing the base construction level of the new slipway
Drone shot: A top down view showing progress on the rock armour

The latest contractor’s progress report highlights several important milestones:

Rock armour installation

Work on the protective rock armour around the development is progressing, helping to form a robust structure along the seaward face.

Slipway foundations

Geogrid and stone layers are being installed to build up and strengthen the base of the new slipway area.

Culvert extension

Sections of the culvert pipe have been installed, with further work planned to complete the extension.

Materials delivered

Around 3,900 tonnes of stone were brought to site during September alone.

These stages form an important part of preparing the site for the next phase of construction, including the installation of the slipway’s structural components.

Specialists use large machinary to arrange the rocks to form a stable rock armour structure

‍

What happens next?

The planned work includes continuing the stone fill and rock armour, completing the culvert extension and progressing towards installation of the precast slipway slabs.

We’ll continue sharing updates as the development progresses, including photographs from the site and information about what the project will mean for Tarbert Harbour.